Gelephu airport. Small today, big in 2029.

A 1,506 m runway with flights to Kolkata now. A 3,000 m runway on the same site from December 2029.

By Sebastian Kaiser · Last verified 8 November 2026

Independent guide. Inner Bhutan is not affiliated with Gelephu Mindfulness City, the GMC Authority or the Royal Government of Bhutan. We summarise official sources and link to them.

The new airport, as of 8 November 2026
Site4 km² across the Paitha River, Sarpang Dzongkhag, next to today's airfield; the river runs through a box culvert under the runway
Runway3,000 m, CAT I, Code 4E, with an Instrument Landing System
AircraftA321 and B737 at the start, wide-bodies later
Capacity1.3 million passengers a year at first, expandable to 5.5 million
DesignBjarke Ingels Group (BIG); NACO as airport consultant for the concept
Airfield contractorRigsar-Vajra Joint Venture (awarded 3 October 2026)
OpeningOfficial inauguration planned for 17 December 2029

It is easy to read about "Gelephu International Airport" and think of two different places. It is one site in two stages. The Bhutanese reported the 2024 plan in March of that year: the new runway runs from near the Paitha Khola to the Aiepoly river, about 50 to 60 m higher than today's runway and farther from the Indian border, and the current airfield will eventually disappear under landfill for the new one. Until then it stays in use.

Flying to Gelephu today

The existing airport (ICAO code VQGP) sits 2 km north-west of Gelephu town at about 300 m above sea level. Its runway is 1,506 m long and visual flights only. It received an aerodrome certificate from the Bhutan Civil Aviation Authority in September 2023, and on 8 December 2025 Drukair flew Gelephu to Kolkata and back for the first time. Scheduled flights started on 12 December 2025.

Drukair at Gelephu, November 2026 timetable
DayFlightRoute and times
Monday, FridayKB210Paro 11:00, Gelephu 11:40; Gelephu 12:10, Kolkata 13:10
Monday, FridayKB211Kolkata 13:50, Gelephu 15:20; Gelephu 15:50, Paro 16:30
WednesdayKB020 / KB021Paro 09:30, Gelephu 10:10; Gelephu 10:40, Paro 11:20

Traffic is still small. The National Statistics Bureau counted 1,094 passengers from Paro to Gelephu and 1,220 the other way in 2025, and 53 on the Kolkata route in its first weeks that December.

Not Indian or Bhutanese? We have found no official confirmation that immigration at Gelephu airport can process other passports. The 2023 aeronautical publication for the airport listed customs and immigration as not available, and GMC says facilities for third-country nationals at the new land-border terminal will come "at a later stage" (22 October 2026). Confirm with your tour operator before you book. Visa rules are in our visa guide.

The new airport

His Majesty The King marked the start of construction on 8 July 2025, with more than a thousand Desuup and Gyalsup volunteers. GMC's published timeline: earthworks from July 2025, main construction from June 2026, aerodrome certification from July 2028, terminal finished in March 2029, operational readiness (ORAT) from July 2029 and the official inauguration on 17 December 2029, Bhutan's National Day.

The terminal design is by BIG, the Danish architects who also drew the GMC masterplan. It takes its cue from Bhutan's four forest types and uses glued timber beams with a diamond motif; BIG showed it at the 2025 Venice Architecture Biennale. On 3 October 2026 GMCA awarded the airfield package (runway, taxiways, aprons, lighting, control tower) to the Rigsar-Vajra Joint Venture, which already does the earthworks. GMC expects more than 800 workers on the airfield at peak. The passenger terminal contract was still to be awarded at that point.

Who pays

GMC has not published a total cost. Two pieces are known: the GMC Nation Building Bond, sold only to Bhutanese citizens in 2025, raised Nu 3.347 billion from 35,403 investors for the airport. And in his 2024 National Day Address the King said Bhutanese in Australia, the United States and Canada had pledged nearly USD 140 million to the project.

Bhutan has asked India for two extra air routes so that Gelephu flights need not route via Paro (The Bhutanese, January 2025). On the ground, India's Prime Minister announced an Indian immigration checkpoint near Gelephu in November 2025 (Business Bhutan). GMC's own plan lists a rail link to India for 2030; see the masterplan.

Questions people ask

When will the new Gelephu airport open?
GMC plans the official inauguration for 17 December 2029. In October 2026 it confirmed a December 2029 opening after awarding the airfield contract.
Can I fly to Gelephu now?
Yes. Drukair flies Paro, Gelephu and Kolkata on Mondays and Fridays and Paro to Gelephu and back on Wednesdays (November 2026 timetable). From Kolkata, entry is confirmed only for Indian and Bhutanese passport holders; others should fly in via Paro or check with their tour operator.
How long is the runway of the new airport?
3,000 m, CAT I, Code 4E, with an Instrument Landing System, for A321 and B737 at first and wide-body aircraft later.
Who designed Gelephu International Airport?
Bjarke Ingels Group (BIG), with NACO as airport consultant for the concept design.
Can foreign tourists enter Bhutan at Gelephu airport?
Not confirmed. We found no official statement that immigration at Gelephu can process passports other than Indian and Bhutanese. Check with your tour operator first.

Not yet confirmed

Related

Sources

  1. GMC: Gelephu International Airport construction begins (8 Jul 2025), accessed 8 November 2026
  2. GMC: GMCA awards airfield construction contract for Gelephu International Airport (3 Oct 2026), accessed 8 November 2026
  3. GMC: The plan, Ancient Future (6 May 2025), accessed 8 November 2026
  4. NACO: Pre-concept and concept design for Gelephu International Airport, accessed 8 November 2026
  5. The Bhutanese: ADB masterplan model selected for Gelephu Airport (16 Mar 2024), accessed 8 November 2026
  6. Department of Air Transport: AIP AD 2, Gelephu (VQGP) (PDF) (28 Dec 2023), accessed 8 November 2026
  7. BBS: Gelephu International Airport resumes domestic operations (7 Jan 2024), accessed 8 November 2026
  8. GMC: First international flight launched from Gelephu International Airport (8 Dec 2025), accessed 8 November 2026
  9. Drukair: Flight schedule, November 2026 (PDF), accessed 8 November 2026
  10. National Statistics Bureau: Statistical Yearbook 2025 (PDF), accessed 8 November 2026
  11. GMC: GMC Nation Building Bond surpasses expectations (6 Jun 2025), accessed 8 November 2026
  12. GMC: His Majesty The King's 2024 National Day Address (17 Dec 2024), accessed 8 November 2026
  13. GMC: GMC Immigration Terminal opens with automated e-gates (22 Oct 2026), accessed 8 November 2026
  14. The Bhutanese: Bhutan puts in request for two air routes important to GMC airport (4 Jan 2025), accessed 8 November 2026
  15. Business Bhutan: PM Modi announces immigration checkpoint near Gelephu (17 Nov 2025), accessed 8 November 2026